Figure 11: Preparation taskflow
Preparation workflow navigation
Installing the Linux base on page 67
Verifying the Enterprise network on page 71
Table 9: Preparation times on page 66 shows the estimated times for completing
each of the above procedures.
Table 9: Preparation times
Workflow Time to complete task
Installing the Linux Base 20 minutes per server
Verifying the enterprise network 5 minutes per server